Improvement of water supply to Huete and Valdemoro del Rey (Cuenca, Spain)

Location : Cuenca
Start Date : 02 April 2007
End Date : 25 July 2010
Budget : € 2,345,700
Status :

Overview

Operations include 31 Km of PVC pipe of differet pressures isntallation and their vents, drainages, valves, inspection chabers and manholes.

The main action for this conduction includes, the crossing under the Madrid-Cuenca railway, the stad with its pumping equipment, a camera break pressure and a new pressure regulating reservoir for the town of Huete, with capacity for 1000 m3.

These actions have improved the supplies to Huete quality and quantity.